Principal of St. Joseph's Technical Institute for the Deaf, Nyang'oma Accused of Misusing Funds — Auditor-General :Stealing From The deaf"
Colleta Omondi: Corrupt to the core
Sister Conslata Aloo: Great pretender but corrupt
The latest report from the Auditor General on St. Joseph's Technical Institute For The Deaf - Nyang'oma, for the year ended 30 June, 2025, has uncovered significant issues.
These include rampant corruption,
embezzlement of public funds, fraudulent procurement practices, and financial
mismanagement attributed to the institution's principal, Mrs. Colleta
Omondi.
According to the report, Mrs. Omondi bears
full responsibility for the financial turmoil, which has been described as
'exploiting the deaf'.
Allegations suggest that she has been
closely collaborating with the board chairperson, Sister Conslata A. Aloo,
while excluding other board members from their dealings. There is growing
pressure for Mrs. Omondi to step down, allowing for impartial investigations by
the Ethics and Anti-Corruption Commission and the Directorate of Criminal
Investigations (DCI) to uncover the scandal that is hindering the institute's
progress.
Regrettably, the once thriving institute
has deteriorated significantly due to corruption, mismanagement, and financial
malpractice attributed to the principal and the chairperson. The two
individuals have conspired to ensure that contracts are awarded to companies in
which they have a vested interest like Techub Control, or that they control
indirectly, manipulating bid amounts to include their own shares and kickbacks.
It has come to light that businesses
operating in Bondo sub-county, where the institute is situated, are
consistently overlooked for tenders. Instead, the principal and the chairperson
favor companies from their places of birth or marriage, disadvantaging local
entrepreneurs who could otherwise benefit from the institute.
Over
expenditure on Repairs and Maintenance: Who benefited from the extra Sh3,002,282?
The
financial statements disclose a repair, maintenance, and improvement
expenditure of Kshs.6,960,152. Upon analysis, it was found that the
management exceeded the approved budget of Kshs.3,957,830 by
Kshs.3,002,282. No explanation was provided for this over
expenditure. As a result, the accuracy, legality, and completeness of the
repairs and maintenance expenditure of Kshs.6,960,152 could not be confirmed.
lrregular
Award of Tender
The Property, Plant and Equipment category includes an amount of Kshs.278,000 allocated for the procurement and delivery of a wood bandsaw machine intended for training purposes in August and September 2024.
Upon reviewing the procurement process, it was found that the Request for Quotation (RFQ) method was utilized, and Techub Control was awarded the tender despite not being listed as a prequalified supplier.
This action is in conflict with Section
106(2) of the Public Procurement and Assets Disposal Act, 2015, which
stipulates that the accounting officer of a procuring entity should allocate
the request to registered suppliers. Consequently, the management's
decision was in violation of the law.
Termination of the Stalled Project- Kopolo
Campus
As previously reported, the Kopolo Campus
project was initiated and financed by the Ministry of Education in 2018 but
stalled in 2019. The proposed twin workshop, classrooms, and office block under
Tender No. SJTTI/OO112018-2019 was awarded to a local contractor on 3 July,2018
at a contract sum of Kshs.53,470,287, with an expected completion period of one
(1) year.
Proposed Construction of a Hospitality
Block
The capital work in progress includes newly added assets for the proposed construction of a Hospitality Block, amounting to Kshs.80,039,745.17 out of a total contract sum of Kshs.92,330,418.
The project for the Hospitality Block was procured and funded by the Ministry of Education- SDTVET, with a commencement date of 13 October, 2023, and a completion date of 30 October, 2024.
Additionally, there is an
expected defect liability period that will run up to 30 October, 2025. The site was handed over to the institute on 16 May, 2025,
and the taking over certificate was signed by both parties, namely the
Contractor Chaju Builders Ltd and the institution. However, the audit confirmed the existence of several pending
issues.
i.
The principal letter to the
project consultant (M/s Dama Services Ltd) dated 27 May 2025 identified some
snag lists that needed to be rectified for the building to be in a usable
state. This letter was after handing over of the site.
ii.
ii. However, as at the time of
audit on November, 2025, the contractor had not rectified some of the pending
issues such as; a) External works main entrance section including paving slabs.
b) Pending works to the grease trap.
c)
External paint works; paint an additional coat to the exterior surfaces, make
repairs to cracks appearing to window putty, paint additional coats to steel
windows and steel doors. d) Plaster and paint the section of the partition wall
showing at the window on first floor hallway.
e)
Plumbing provision in the kitchen.
f)
Complete installing signages to washrooms and ducts.
g)
Repaint all curtain rods.
h)
Paint internally all steel doors and windows as per specifications.
i)
All doors to be sanded and revarnished.
j)
Complete roof gutter.
k) Complete the tiling of internal walls in the laundry area, kitchen area and ablution walls at the washroom areas.
l)
lnstall all mechanical and plumbing works to completion as per the Mechanical
Engineers specifications and any other defects noted in the snag list.
ln
the circumstances, the delayed completion of pending works may render the
building partially unusable, affecting planned service delivery and
consequently deterioration of uncorrected works may lead to future premature
repair and maintenance costs.
Cash Procurement Using lmprest
An examination of the sampled payment
vouchers related to Repairs and Maintenance expenses indicated that Management
had issued imprests amounting to Kshs.863,311 to various officers for the cash
acquisition of goods and services.
It was also observed that certain procured
items surpassed the permissible low value procurement threshold of Kshs.50,000
per item within a financial year.
Additionally, the review of the surrender
documents showed that the imprest holders failed to keep an updated memorandum
cash book, and the receipts lacked support from electronic tax register
receipts. Cash purchases heighten the risk of fraudulent receipts for
non-existent items, making them vulnerable to misuse.
In light of these circumstances, the
utilization of a framework agreement for the supply of goods and services would
have been a more suitable option.


Comments
Post a Comment